Answer:
7 kanban containers are required
Step-by-step explanation:
Given the following information :
Average Waiting time for containers = 0.2 days
Average processing time = 0.1 days / container
Daily usage (Demand rate) = 100 per day
Container capacity = 5 housings
Policy variable ( Alpha) = 10% = 0.1%
The required number of Kanban containers required by Jones Electric Motor can be calculated thus :
[Number of containers(x) * container size] = (Demand rate (waiting time + processing time)*(1 + alpha))
x * 5 = (100 * (0.2 + 0.1)*(1 + 0.1))
5x = [100 * (0.3)*(1.1)]
5x = [100 * 0.33]
5x = 33
x = 33 / 5
x = 6.6 containers
x = 7