A process that is considered to be in control measures an ingredient in ounces. Below are the last ten samples (each of size n=5) taken. The population standard deviation is 1.36.

SAMPLE
1 2 3 4 5 6 7 8 9 10
5 6 9 10 9 10 9 12 8 9
8 9 9 8 12 11 9 9 6 10
6 8 5 7 10 8 10 9 4 12
4 7 3 8 8 6 12 10 4 11
5 4 2 9 8 6 8 6 5 7
Using information from the above table:
Calculate the standard deviation of the sample means, σ×.
Determine the control limits for the mean chart, using A2 and σ× if z=3.
Determine the control limits for the range chart.
Construct mean (using A2) and range control charts by using information from (ii) and (iii).
Comment on your results.

User Raju Kunde
by
4.9k points

1 Answer

5 votes

Answer:

nu

bartleby

search

message

Q&A

Sign in

Business

Operations Management

Q&A Library

Question : A process that is considered to be in control measures an ingredient in ounces. Below are the last ten samples (each of size n=5) taken. The population standard deviation is 1.36. SAMPLE 1 2 3 4 5 6 7 8 9 10 5 6 9 10 9 10 9 12 8 9 8 9 9 8 12 11 9 9 6 10 6 8 5 7 10 8 10 9 4 12 4 7 3 8 8 6 12 10 4 11 5 4 2 9 8 6 8 6 5 7 Using information from the above table: Calculate the standard deviation of the sample means, σ×. Determine the control limits for the mean chart, using A2 and σ× if z=3. Determine the control limits for the range chart. Construct mean (using A2) and range control charts by using information from (ii) and (iii). Comment on your results.

Question : A process that is considered to be in control measures an ingredient in ounces. Below are the last ten samples (each of size n=5) taken. The population standard deviation is 1.36. SAMPLE 1 2 3 4 5 6 7 8 9 10 5 6 9 10 9 10 9 12 8 9 8 9 9 8 12 11 9 9 6 10 6 8 5 7 10 8 10 9 4 12 4 7 3 8 8 6 12 10 4 11 5 4 2 9 8 6 8 6 5 7 Using information from the above table: Calculate the standard deviation of the sample means, σ×. Determine the control limits for the mean chart, using A2 and σ× if z=3. Determine the control limits for the range chart. Construct mean (using A2) and range control charts by using information from (ii) and (iii). Comment on your results.

close

50% off! Get your first month of bartleby learn for only $4.99

arrow_forward

Question

Asked Apr 22, 2020

360 views

Question :

A process that is considered to be in control measures an ingredient in ounces. Below are the last ten samples (each of size n=5) taken. The population standard deviation is 1.36.

SAMPLE

1

2

3

4

5

6

7

8

9

10

5

6

9

10

9

10

9

12

8

9

8

9

9

8

12

11

9

9

6

10

6

8

5

7

10

8

10

9

4

12

4

7

3

8

8

6

12

10

4

11

5

4

2

9

8

6

8

6

5

7

Using information from the above table:

Calculate the standard deviation of the sample means, σ×.

Determine the control limits for the mean chart, using A2 and σ× if z=3.

Determine the control limits for the range chart.

Construct mean (using A2) and range control charts by using information from (ii) and (iii).

Comment on your results.

check_circle

Expert Answer

Step 1

Note- We’ll answer the first three subparts of the question since the exact one wasn’t specified. Please submit a new question specifying the one you’d like answered.

Given data,

Samples

Observation

1

2

3

4

5

6

7

8

9

10

1

5

6

9

10

9

10

9

12

8

9

2

8

9

9

8

12

11

9

9

6

10

3

6

8

5

7

10

8

10

9

4

12

4

4

7

3

8

8

6

12

10

4

11

5

5

4

2

9

8

6

8

6

5

7

Step 2

The method of standard deviation is similar to the population standard deviation.

Operations Management homework question answer, step 2, image 1

The standard deviation of the sample mean can be calculated by the following formula.

Operations Management homework question answer, step 2, image 2

On substituting the given value in the formula.

Operations Management homework question answer, step 2, image 3

Hence, the standard deviation for the sample mean is 0.60

Step 3

Ans 2:

(x-bar) is calculated by calculating the average of given numbers in a column and Range is calculated by subtracting the largest value from the smallest value.

Samples

Observation

1

2

3

4

5

6

7

8

9

10

1

5

6

9

10

9

10

9

12

8

9

2

8

9

9

8

12

11

9

9

6

10

3

6

8

5

7

10

8

10

9

4

12

4

4

7

3

8

8

6

12

10

4

11

5

5

4

2

9

8

6

8

6

5

7

5.6

6.8

5.6

8.4

9.4

8.2

9.6

9.2

5.4

9.8

Range R

(8-4)

= 4

(9-4)

= 5

(9-2)

= 7

(10-7)

= 3

(12-8)

= 4

(11-6)

= 5

(12-8)

= 4

(12-6)

= 6

(8-4)

= 4

(12-7)

= 5

...

Step-by-step explanation: