10. In earned value analysis (EVA), we found: SV = -$7,800 at certain point. If the project has a total budget = $65,000 and total duration of 25 days. The project is: a. On schedule b. Ahead of schedule by 0.33 day c. Ahead of schedule by 3 days d. Behind schedule by 0.33 day e. Behind schedule by 3 days