Answer:
budgeted costs for direct materials
budgeted direct manufacturing labor
budgeted manufacturing overhead
Step-by-step explanation:
Direct materials costs are $4.00 per pool cue.
Direct manufacturing labor is $6.00 per pool cue.
Manufacturing overhead is $0.84 per pool cue.
total budgeted direct materials = 22,000 x $4 = $88,000
total budgeted direct labor = 22,000 x $6 = $132,000
total budgeted manufacturing overhead = 22,000 x $0.84 = $18,480
The information about the beginning and ending inventories is not relevant to this question since it only deals with budgeted or estimated costs which may or may not differ from actual costs.