Answer:
d) 0.750
Step-by-step explanation:
The computation of the correct value for the resulting line's efficiency is shown below:
Efficiency = All task times sum ÷ (Actual number of workstations × cycle time)
where,
All task times sum is 60 minutes
The Actual number of workstations is 8
And, the cycle time is
Since 600 seconds = 10 minutes
And 1 minute = 60 seconds
So, the cycle time would be
= 600 ÷ 60
= 10 minutes
Now placing these values to the above formula
So, the resulting line's efficiency is
= 60 ÷ (8 × 10)
= 60 ÷ 80
= 0.750