Answer:
Demron
Outsourcing welding or Purchasing a welding machine for in-house welding:
Cost of outsourcing:
Variable cost = $1.50 x 35,000 = $52,500
Fixed cost 45,000
Total outsourcing costs $97,500
Cost of purchasing a welding machine:
Fixed cost = $13,500
Maximum Variable costs = $84,000
Total in-house cost = $97,500
Maximum variable cost per weld
= $84,000/35,000
= $2.40
Step-by-step explanation:
This problem of outsourcing welding activities of Demron Company or buying the welding machine to enable in-house welding is like a make or buy decision challenge. The appropriate approach to tackling this challenge is to determine the total costs under each option. The option that yields the greater outcome is chosen. However, for Demron's case, a determination of the maximum variable costs that are acceptable for in-house option to be selected is made. The level required for this determination is the level of costs that makes no difference between outsourcing and in-housing welding.