Answer: a) The equivalent units for material = 1,100
The equivalent units for conversion cost = 924.
b) The unit cost for material and conversion cost is $5.84 and $26.56 respectively.
c) cost reconciliation schedule is in the explanation column
Step-by-step explanation:
first , we calculate units in process
Units in Process = Units of applications Opened + units of application started - units of application completed
= 170 + 930 - 660 = 440 units
Equivalent units of production for materials =application units completed + Application units in process x its percentage complete
660 + (440 x 100%)=660+440= 1,100
Equivalent units of production for conversion = application units completed + Application units in process x its percentage complete
660 + (440 x 60%)=660+264=924
Computing the unit costs
Units of cost as per material
Number of application units during the month = 660units
Wor in process unit = 440units
Material cost during ,month -=$5,114
Beginning work in progress cost for materials =$1,310
Equivalent unts of production for materials = 1,100
Unit cost for material = Material cost during the month +Begining work in progress cost for materials/Equivalent units of production for materials = $5,114 + $1,310=$6,424/ 1100= $5.84
Units of cost as per conversion
Number of application units during the month = 660units
Work in progess unit = 440units
conversion cost during ,month -= direct labour + overhead = $12,820 + $7,581= $20, 401
Beginning work in progress cost for materials =$4,140
Equivalent unts of production for materials = 924
Unit cost = Material cost during the month +Beginning work in progress cost for materials/Equivalent units of production for materials = $20,401 + 4,140=$24,541 / 924= $26.56
Cost Reconciliation schedule
Particulars no of units materials conversion Total
units transferred 660 $5,114 $20,401 $25,515
ending WIP 440 $6,424 $24, 541 $30,965
Total $11,538 $44,942 $56,480