a) While excavating, the Contractor hits a rock layer. Since the plans and soil report did not mention such rock, the contractor files a claim under: i. Force majeure. ii. Differing site conditions. iii. Design errors/omissions. iv. Unusual weather conditions. v. Changes in owner’s requirements.

User Natarsha
by
3.3k points

1 Answer

3 votes

Answer:

Differing site conditions

Step-by-step explanation:

A differing site condition is a condition that has been changed. Since the plan did not mention this rock, the contractor can file a claim under this.

It is a hidden physical condition that is discovered at a site which is actually different from what was expected. It can also be regarded as unforeseen site condition.