Answer: iii. A schedule prepared by the contractor after the project had fallen behind with adjustments that expedite the remainder of the project to ensure a timely finish
Step-by-step explanation:
The recovery schedule is a method of recovering time by the contractor. Just like the progress schedule, it should be noted that the recovery schedule is the responsibility of a contactor.
Therefore, it is a schedule prepared by the contractor after the project had fallen behind with adjustments that expedite the remainder of the project to ensure a timely finish.