1. An updated schedule is: a. A schedule that reflects new design modifications. b. A revised schedule reflecting project information at a given data date regarding completed activities, in-progress activities, and changes in future work. c. A schedule that incorporates subcontractors’ schedules. d. A schedule with resources and budget.

1 Answer

2 votes

Answer: A revised schedule reflecting project information at a given data date regarding completed activities, in-progress activities, and changes in future work

Step-by-step explanation:

An updated schedule is a schedule which has been carefully analysed and revised and hence reflects the information regarding a project at a given data date regarding the activities that have already been completed, the activities that are still in progress and the changes that will be made in the future work.