Answer:
1. Calculate the NPV for each option available for the project. (Do not round intermediate calculations. Enter your answers in dollars, not millions of dollars, e.g. 1,234,567.)
- go to market now = $744,000
- focus group = $852,000
- consulting firm = $916,000
2. Which action should the firm undertake?
The NPV is higher than the rst of the options.
Step-by-step explanation:
expected payoffs:
- option 1 (go to market now) = (40% x $1.86 million) + 0 = $744,000
- option 2 (focus group) = (55% x $1.86 million) + 0 = $1,023,000
- option 3 (consulting firm) = (70% x $1.86 million) + 0 = $1,302,000
expected NPVs:
- option 1 (go to market now) = $744,000
- option 2 (focus group) = $1,023,000 - $171,000 = $852,000
- option 3 (consulting firm) = $1,302,000 - $386,000 = $916,000
go to market now