Ultimate Corporation uses a standard cost system for the production of its water ski radios. The direct labor standard for each radio is 0.9 hours. The standard direct labor cost per hour is $7.20. During the month of August, Zanny's water ski radio production used 6,600 direct labor-hours at a total direct labor cost of $48,708. This resulted in the production of 6,900 water ski radios for August. What is Zanny's labor rate variance for August?

a. $2,808 Unfavorable
b. $1,188 Unfavorable
c. $972 Favorable
d. $2,160 Favorable

1 Answer

2 votes

Answer:

Direct labor rate variance= $594 unfavorable

Step-by-step explanation:

Giving the following information:

The standard direct labor cost per hour is $7.20.

During August, Zanny's water ski radio production used 6,600 direct labor-hours at a total direct labor cost of $48,708.

To calculate the direct labor rate variance, we need to use the following formula:

Direct labor rate variance= (Standard Rate - Actual Rate)*Actual Quantity

Actual rate= 48,078/6,600= $7.29

Direct labor rate variance= (7.20 - 7.29)*6,600

Direct labor rate variance= $594 unfavorable

User Ryan Kaskel
by
7.3k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories