Answer:
The amount of the initial cash flow for this expansion project is $15,000.
Step-by-step explanation:
It is important to remember that Sunk costs are not relevant for decision making.
Sunk Cost are costs already incurred as a results of past decisions.
The Cost of Land of $300,000 and the Cost of Equipment Valued at $30,000 are both Sunk costs and are not relevant for this expansion project.
The Relevant Costs (Initial Cash Flow) is $15,000 for modifications.