Answer:
Instructions are below.
Step-by-step explanation:
Giving the following information:
Direct material:
Standard= 7.40 pounds $ 2.60 per pound
Actual= 12,100 pounds of material were purchased for $2.50 per pound.
Direct labor:
Standard= 0.45 hours $ 8.00 per hour
Actual= 575 hours of direct labor time were recorded at a total labor cost of $5,750
Units produced= 1,500
To calculate the direct material price and quantity variance, we need to use the following formulas:
Direct material price variance= (standard price - actual price)*actual quantity
Direct material price variance= (2.6 - 2.5)*12,100
Direct material price variance= $1,210 favorable
Direct material quantity variance= (standard quantity - actual quantity)*standard price
standard quantity= 1,500*7.4= 11,100
Direct material quantity variance= (11,100 - 12,100)*2.6
Direct material quantity variance= $2,600 unfavorable
To calculate the direct labor efficiency and rate variance, we need to use the following formulas:
Direct labor time (efficiency) variance= (Standard Quantity - Actual Quantity)*standard rate
Standard quantity= 1,500*0.45= 675
Direct labor time (efficiency) variance= (675 - 575)*8
Direct labor time (efficiency) variance= $800 favorable
Direct labor rate variance= (Standard Rate - Actual Rate)*Actual Quantity
Actual rate= 5,750/575= $10
Direct labor rate variance= (8 - 10)*575
Direct labor rate variance= $1,150 unfavorable