Answer:
PRESENT APPROACH
Value-added time 20min
Add Non-value-added time 905 min
Total lead time 925 min
Value-added ratio (as a percent) 2.2%
PROPOSED APPROACH
Value-added time 20min
Non-value-added time 50 min
Total lead time 70 min
Value-added ratio (as a percent) 28.6%
Explanation:
PRESENT APPROACH
Calculation for Value added time
Using this formula
Value added time = Total time of all steps
Value added time= 5 + 8 + 4 + 3 = 20 min
Calculation for Non-value-added time
Using this formula
Non-value-added time = Batch wait time + Move Time
Hence ,Batch wait time = Value added time * Remaining numbers of units after first unit start
Let plug in the formula
= 20 min * 44
= 880 min
Move Time = 5 * 5 min
= 25 min
Hence, Non-value-added time
= 880 + 25 = 905 min
Calculation for Value-added ratio (as a percent)
Using this formula
Value-added ratio (as a percent) = Value added time/Total lead time * 100
Let plug in the formula
Value-added ratio (as a percent) = 20/925 * 100 = 2.2 %
PROPOSED APPROACH :-
Calculation for Value added time
Using this formula
Value added time = Total time of all steps
= 5 + 8 + 4 + 3 = 20 min
Calculation fo Non-value-added time
Using this formula
Non-value-added time= Batch wait time + Move Time
Batch wait time = Value added time * Remaining no of units after first unit start
Let plug in the formula
Non-value-added time = 20 min * 2
Non-value-added time= 40 min
Move Time = 5 * 2 min
= 10 min
Non-value-added time = 40 + 10
Non-value-added time= 50 min
Calculation for Value-added ratio (as a percent)
Using this formula
Value-added ratio (as a percent) = Value added time/Total lead time * 100
Let plug in the formula
Value-added ratio (as a percent) = 20/70 * 100
Value-added ratio (as a percent) = 28.6 %
Therefore:
PRESENT APPROACH
Value-added time 20min
Add Non-value-added time 905 min
Total lead time 925 min
Value-added ratio (as a percent) 2.2%
PROPOSED APPROACH
Value-added time 20min
Non-value-added time 50 min
Total lead time 70 min
Value-added ratio (as a percent) 28.6%