Answer:
Project B
Step-by-step explanation:
The computation of the net present value is shown below:
For project A
(in dollars) (in dollars)
Year Cash flows Discount factor at 10% Present value
0 -60000 1 -60000.00 (A)
1 30000 0.9090909091 27272.73
2 27000 0.826446281 22314.05
3 20000 0.7513148009 15026.30
Total present value 64613.07 (B)
Net present value 4613.07 (B - A)
For project B
(in dollars) (in dollars)
Year Cash flows Discount factor at 11% Present value
0 -60000 1 -60000.00 (A)
1 0 0.9009009009 0
2 80000 0.8116224332 64929.79
3 0 0.7311913813 0
Total present value 64929.79 (B)
Net present value 4929.79 (B - A)
As we can see that project B has high net present value as compared with project A so project B should be accepted