Answer:
The predetermined overhead rate for the recently completed year was closest to: $11.54 per machine-hour
Step-by-step explanation:
Predetermined Overheads = Budgeted Fixed Overheads / Budgeted Activity
= $ 838,730 / 72,700
= $11.536864 or $11.54 per machine-hour.