Answer:
The answer is "21,622.98".
Step-by-step explanation:
In the given question some information is missing, which can be defined in the given attachment.
To calculate the first cost we first subtract B cost is to X.
NPV = Cash Flow of the sum of PV amount




The value of Option A or NPV = -24,575.88
The value of Option B or NPV:


The value of Option B or NPV = -X -2952.9
As demanded
In Option B the value of NPV = In Option A the value of NPV
