Answer:
The answer is "21,622.98".
Step-by-step explanation:
In the given question some information is missing, which can be defined in the given attachment.
To calculate the first cost we first subtract B cost is to X.
NPV = Cash Flow of the sum of PV amount
![PV = \frac{Flow of cash} {(1+i)^n} \\\\ \ Calculating \ the \ NPV \ of \ option \ A: \\\\](https://img.qammunity.org/2021/formulas/business/college/i77z9loxgpolvvtgasibvyq056z3c297pi.png)
![= (-16600)/((1 + 0.08)^0)-(2400)/((1 + 0.08)^1)-(2400)/((1 + 0.08)^2) -(2400)/((1 + 0.08)^3)-(2400)/((1 + 0.08)^4)](https://img.qammunity.org/2021/formulas/business/college/88w34ytft4wxvxe8ca4sa4l5u0d8nznb2n.png)
![= (-16600)/(1)-(2400)/(1.08)-(2400)/(1.16)-(2400)/(1.25)-(2400)/(1.36)](https://img.qammunity.org/2021/formulas/business/college/bqsvd1a9c96vquj8vag42xra01bz2do7if.png)
![=-16600-2222.22-2068.96-1920-1764.70\\\\=-24,575.88](https://img.qammunity.org/2021/formulas/business/college/gmqntqs0526zpksotrvypcv5bb04ui366s.png)
The value of Option A or NPV = -24,575.88
The value of Option B or NPV:
![=-(X)/((1 + 0.80)^0)-(1000)/((1 + 0.08)^1) -(1000)/((1 + 0.08)^2)-(1000)/((1 + 0.08)^3)-(1000)/((1 + 0.08)^4) \\\\ =-(X)/((1.80)^0)-(1000)/((1.08)^1) -(1000)/((1.08)^2)-(1000)/((1.08)^3)-(1000)/((1.08)^4)](https://img.qammunity.org/2021/formulas/business/college/li4rvb4c5j3tucb0ppp1yyo8edrax78kyr.png)
![= -(X)/(1)-(1000)/(1.08)-(1000)/(1.16)-(1000)/(1.25)-(1000)/(1.36)\\\\= -X -555.55-862.06-800-735.29\\\\=-X -2952.9](https://img.qammunity.org/2021/formulas/business/college/1u4h8xuve0iyabbkx0co71bj01j5dtzmgw.png)
The value of Option B or NPV = -X -2952.9
As demanded
In Option B the value of NPV = In Option A the value of NPV
![-X -2952.9= -24,575.88\\\\-X= -21,622.98\\\\X=21,622.98\\](https://img.qammunity.org/2021/formulas/business/college/yjew8w35pgbfr1ihp0hbhjr3ssn23be0x4.png)