Factory Overhead Rates, Entries, and Account Balance Eclipse Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning August 1 $18,500,000 $44,000,000 Estimated direct labor hours for year 800,000 Estimated machine hours for year 1,250,000 Actual factory overhead costs for August $1,515,800 $3,606,300 Actual direct labor hours for August 64,500 Actual machine hours for August 105,000 a. Determine the factory overhead rate for Factory 1. Round your answer to two decimal places.

1 Answer

5 votes

Answer:

Predetermined manufacturing overhead rate= $14.8 per machine hour

Step-by-step explanation:

Giving the following information:

Factory 1

Estimated factory overhead= $18,500,000

Estimated machine hours for year 1,250,000

To calculate the predetermined manufacturing overhead rate we need to use the following formula:

Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base

Predetermined manufacturing overhead rate= 18,500,000/1,250,000

Predetermined manufacturing overhead rate= $14.8 per machine hour