It takes 4 people 2 days to paint a wall. How long would it take if we got 8 people to do it?

2 Answers

3 votes

Answer:

1 day

Explanation:

4 people = 2 days

→ Work out how long 1 person takes

4 people = 2 days

( ÷ 4 ) ( × 4 )

1 person = 8 days

→ Work out how long 8 people can do it

1 person = 8 days

( × 8 ) ( ÷ 8 )

8 people = 1 day

User Saste
by
4.5k points
4 votes

Answer:

if it takes 4 people for 2 days

4+4= 8

so it would only take 8 people for 1 day

User Sauronnikko
by
4.7k points