Job 910 was recently completed. The following data have been recorded on its job cost sheet: Direct materials $ 2,429 Direct labor-hours 74 labor-hours Direct labor wage rate $ 17 per labor-hour Machine-hours 135 machine-hours The Corporation applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $18 per machine-hour. The total cost that would be recorded on the job cost sheet for Job 910 would be:

1 Answer

4 votes

Answer:

Total Job Cost is $6,117

Step-by-step explanation:

The total cost of the Job 910 is as under:

Direct Material Cost $2,429

Direct Labor Cost (74 Labor Hrs * $17 per Labor Hour) $1,258

Applied overhead (135 Machine Hrs * $18 per Machine Hr) $2,430

Total Job Cost $6,117