Answer:
$11.58 per machine hour
Step-by-step explanation:
Given that: Estimated Manufacturing overhead cost =$235,000, Actual manufacturing overhead cost = $244,200 Estimated machine hours = 20,300, Actual machine hours= 22,700
The predetermined manufacturing overhead rate per machine hour = Estimated manufacturing overhead cost / Estimated machine hours
= $235,000 / 20,300
= $11.5763
= $11.58 per machine hour