173k views
0 votes
Strange Manufacturing Company is purchasing a production facility at a cost of $21 million. The firm expects the project to generate annual cash flows of $7 million over the next five years. Its cost of capital is 18 percent. What is the net present value of this project

User Hubert
by
5.5k points

1 Answer

4 votes

Answer:

NPV = $0.89 million

Step-by-step explanation:

The net present value is an important concept in evaluation a project. It calculates the return a project provides when discounted at the required rate. The initial cost involved in the project is deducted from the discounted cash flows provided by the project and if the NPV is positive, the project should be proceeded with.

The formula for NPV is,

NPV = CF1 / (1+r) + CF2 / (1+r)^2 + ... + CFn / (1+r)^n - Initial outlay

NPV = 7 / (1+0.18) + 7 / (1+0.18)^2 + 7 / (1+0.18)^3 + 7 / (1+0.18)^4 + 7 / (1+0.18)^5 - 21

NPV = $0.89 million

User Mppf
by
5.7k points