Answer:
i. 18 days
ii.
part of work
iii.
part of work
Explanation:
i.
part of work can be done in 6 days.
Days taken to complete the whole work:
= 6 * 3
= 18 days
ii. Whole work will be done in 18 days.
So, 1 day work =

iii. Work done in 9 days :


So, remaining work :



part of work