Answer:
Predetermined manufacturing overhead rate= $12.1 per direct labor hour
Step-by-step explanation:
Giving the following information:
Estimated total fixed manufacturing overhead= $121,000
Estimated direct labor hours= 10,000
To calculate the predetermined manufacturing overhead rate we need to use the following formula:
Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Predetermined manufacturing overhead rate= 121,000/10,000
Predetermined manufacturing overhead rate= $12.1 per direct labor hour