Answer:
Work In Process : Job 11-101 $4,640 (debit)
Work In Process : Job 11-102 $5,510 (debit)
Work In Process : Job 11-103 $6,612 (debit)
Work In Process : Job 11-104 $12,760 (debit)
Work In Process : Job 11-105 $18,270 (debit)
Work In Process : Indirect labor $12,500 (debit)
Salaries Payable $60,292 (credit)
Step-by-step explanation:
The factory labor consist of direct labor and indirect labor and all are accounted in the work in process account.
Direct labor can be traced directly to the job being manufactured.
Whilst indirect labor can not be traced directly to the job being manufactured example is factory supervisor`s salary.