Answer:
Total cost= $8,606
Step-by-step explanation:
Giving the following information:
Job 450:
Direct materials= $2,108
A total of 36 direct labor-hours and 234 machine-hours were worked on the job.
The direct labor wage rate is $18 per labor-hour.
The predetermined overhead rate is $25 per machine-hour.
We need to calculate the total cost for Job 450:
Direct materials= 2,108
Direct labor= 36*18= 648
Overhead= 234*25= 5,850
Total cost= $8,606