Answer:
Standard cost direct material= $5.4 per square foot
Step-by-step explanation:
Giving the following information:
The current cost of cedarwood is $ 5.00 per square foot from the supplier. Delivery costs are $ 0.40 per square foot.
When calculating the standard costs of direct materials, you need to take into account the freight in costs.
Standard cost direct material= 5 + 0.4
Standard cost direct material= $5.4 per square foot