Answer:
Instructions are below.
Step-by-step explanation:
Giving the following information:
Standard Custom
Direct Labor cost 60,000 $ 12,000
Machine Hours 1,500 1,500
Set-up Hours 100 500
The total estimated overhead costs are $342,000.
A. First, we need to calculate the predetermined overhead rate:
Total direct labor cost= $72,000
Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Predetermined manufacturing overhead rate= 342,000/72,000
Predetermined manufacturing overhead rate= $4.75 per direct labor dollar
Standard= 4.75*60,000= $285,000
Custom= 4.75*12,000= $57,000
B. Now, we need to calculate a predetermined overhead rate for each activity:
Machining:
Total machine-hours= 3,000
Total overhead= 222,000
predetermined overhead rate= 222,000/3,000
predetermined overhead rate= $74 per machine-hour
Setup:
Total set-up hours= 600
Total overhead= 120,000
predetermined overhead rate= 120,000/600
predetermined overhead rate= $200 per set up-hour
Standard= 74*1,500 + 200*100= $131,000
Custom= 74*1,500 + 200*500= $211,000