The answer : 3780 bolts


Explain

We first calculate the time taken to make nuts and then first number of bolts made in remaining times


Nuts to be made: 750

Nuts made per hour : 500

Time take making nuts = total nuts/ nuts per hour

750/500= 1.5 hours


Time taken making nuts : 1.5 hours
Total time : 8 pm -2 pm :6 pm

Time remaining : 6-15 = 4.5 hours


Time remaining: 4.5 hours
Bolts per hour = 840 bolts

Total bolts made

Time remaining x bolts per hour

840x4.5

= 3780 bolts