Answer:
The number of kanban containers needed for the wheels is 4.2 containers
Step-by-step explanation:
In order to calculate the number of kanban containers needed for the wheels we would have to calculate the following formula:
number of kanban containers needed for the wheels=Demand rate*(Average processing time+Average waiting time)*(1+Alpha)/Container size
According to the given data we have the following:
Demand rate = 2000 per day
Average processing time= 0.15 day
Average waiting time = 0.25 day
Container size= 200
Alpha= 5%
Therefore, number of kanban containers needed for the wheels=2,000*(0.15+0.25)*(1+0.05)/200
number of kanban containers needed for the wheels=4.2 containers
The number of kanban containers needed for the wheels is 4.2 containers