Answer:
2.56 years
Step-by-step explanation:
Payback period calculates the amount of time it takes to recover the amount invested in a project from its cumulative cash flows.
payback period = amount invested / cash flows
cash flows = $510,000 - $360,000 = $150,000
$384,000 / $150,000 = 2.56 years