Construction crews A,B,C and D build a 1200 meter long road. Team A builds 1/2 of the total length built by the other 3 teams. Team B builds 1/3 of the total length built by the other 3 teams. C builds a section that is 1/4 of the length built by the other teams. How many meters did Team D build

1 Answer

6 votes

Answer:

260 meters.

Explanation:

It is given that construction crews A,B,C and D build a 1200 meter long road.


A+B+C+D=1200 ...(1)

Team A builds 1/2 of the total length built by the other 3 teams. So,


A:(B+C+D)=1:2

It means total distance divided in 1:2.


A=1200* (1)/(1+2)=1200* (1)/(3)=400

Similarly,

Team B builds 1/3 of the total length built by the other 3 teams.


B:(A+C+D)=1:3

It means total distance divided in 1:3.


B=1200* (1)/(4)=300

C builds a section that is 1/4 of the length built by the other teams.


C:(A+B+D)=1:4

It means total distance divided in 1:4.


C=1200* (1)/(5)=240

Now, put A=400, B=300 and C=240 in (1).


400+300+240+D=1200


D=1200-940


D=260

Therefore, 260 meters build by D.