Answer:
Scenario D.1
Jerry Allison Plumbing Supplies:
Time between production runs = 2.25 days.
Step-by-step explanation:
With EOQ = 12,000 and working days of 300 per annum
The company can produce 40 units (12,000/300) per day, producing on all the days.
But since the production rate is 90 units per day for the economic production lot size, this can be produced in 133 days (12,000/90). This leaves 167 days as free of production.
Therefore, the company can produce every 2.25 days (90/40), this will give 133 days of production (300/2.25). The time between production runs is therefore 2.25 days. This can be converted into hours, and stated as: the next production run starts after every 54 hours.