A constraint in the model means:__________.

1. activity A should be finished within 2 weeks.
2. the total time taken by activity A cannot be more than 2 weeks.
3. activity A cannot be crashed by more than 2 weeks.
4. activity A must be finished in week 2 after the start of the activity.
5. none of the above.

User Cephas
by
7.9k points

1 Answer

3 votes

Answer:

The correct answer to the given question will be Option C.

Step-by-step explanation:

The YA has been used to describe or portray the period that intervention A crashes for.

The total number of weeks A may malfunction would have been:


normal \ times-crash \ time


5-3


2 \ weeks

then,


Y_(A) <=2 \ means

The other given choices are not related to the given situation. So that option C would be the appropriate choice.

User TheoPlatica
by
8.5k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories