A constraint in the model means:__________.

1. activity A should be finished within 2 weeks.
2. the total time taken by activity A cannot be more than 2 weeks.
3. activity A cannot be crashed by more than 2 weeks.
4. activity A must be finished in week 2 after the start of the activity.
5. none of the above.

User Cephas
by
5.7k points

1 Answer

3 votes

Answer:

The correct answer to the given question will be Option C.

Step-by-step explanation:

The YA has been used to describe or portray the period that intervention A crashes for.

The total number of weeks A may malfunction would have been:


normal \ times-crash \ time


5-3


2 \ weeks

then,


Y_(A) <=2 \ means

The other given choices are not related to the given situation. So that option C would be the appropriate choice.

User TheoPlatica
by
6.7k points