Answer:
1236.15
Explanation:
Data provided
Daily demand (d) = 40 units
Standard deviation = 8 units
Lead time (L) = 30 days
The Service level of 95 percent z value = 1.65
The computation of the reorder point is shown below:-
Reorder point = demand during lead time + safety stock
= 1236.149689
or
= 1236.15
Therefore the correct answer is 1236.15