2 Answers

3 votes

Answer:

480

Step-by-step explanation:

User Daniel Compton
by
8.1k points
3 votes

Answer:

480 hours

Solution,

Time taken by 1 worker to complete the project= 2880 hours

Time taken by 12 workers to complete the project:


(2880)/(12) \\ = 480 \: hours

Hope this helps ...

Good luck on your assignment...