Answer:
Cepeda Corporation
Cost of Goods manufactured schedule for June 2017
Work in process, 6/1/17 $3,820
Direct materials used $21,540
Direct labor $41,680
Work in process, 6/30/17 ($3,930 ) $63,110
Factor Overheads:
Factory utilities $470
Depreciation, factory equipment $1,760
Maintenance, factory equipment $1,860
Indirect materials $2,870
Indirect factory labor $5,230
Factory manager's salary $3,550 $15,740
Total cost of manufactured goods $78,850
Step-by-step explanation:
The cost of goods manufactured is made up of the beginning work in process, direct materials cost, direct labor costs, and factory overheads minus the ending work in process. It is this figure that decides the product cost per unit, which will be a consideration in deciding the selling price in some market situations.