Answer:
The additional worker should be hired.
Step-by-step explanation:
we need to calculate the marginal revenue product and than see if it is higher or lower than the marginal cost of hiring the extra worker.
MRP = MPP x price per unit sold = 4 units per hour x $9 per unit = $36 per hour
Marginal cost = $35 per hour
since the MRP ($36) is higher than the MC ($35), then the additional worker should be hired.