A Scrum Master is extremely busy and getting overwhelmed with a large number of tasks that are waiting for his attention. Can you help the Scrum Master prioritize among the following tasks, that is, which one should he do first?

1. Complete amendments to the definition of done as discussed in the last Sprint retrospective
2. Contact a technical expert with a request to help out a team member who is stuck on a particular
3. Produce a Sprint completion report that is already delayed by 2 days
4. Schedule the next Sprint planning meeting
Explanation:
The Scrum Master has many responsibilities but the most important one is to help the team members who are blocked

1 Answer

1 vote

Answer:

2.

Step-by-step explanation:

Based on the information provided within the question it can be said that the first thing that he should do would be to contact a technical expert with a request to help out a team member who is stuck on a particular. Helping team members is always a top priority for the Scrum master as they need to make sure that everyone is able to properly handle the tasks that are presented, otherwise, everything begins to get backed up and will ultimately crash.