The Corporation applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $14 per machine-hour. What amount wou

1 Answer

3 votes

Question

The question is incomplete, hence the tutor added a piece of information

The Corporation applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $14 per machine-hour. What amount would be

Assuming the actual machine hours worked is 3,500

Note the actual machine was added by the tutor

Answer:

Applied overhead =$49,000

Step-by-step explanation:

Overheads are charged to units produced by the means of an estimated overhead absorption rate. This rate is computed using budgeted overhead and budgeted activity level.

Pre-determined overhead absorption rate (POAR) = Budgeted overhead/Budgeted machine hours

The POAR is given as $14 per machine hour

Applied (absorbed) overhead = POAR × Actual machine hours

Applied overhead = $14 × 3,500 =$49000