Answer:
Project should have minimum annual cash flow of $62,373.06 to accept the project
Step-by-step explanation:
Any project will be accepted if its net present value (NPV) is positive
Hence, NPV>0
Sum of discounted cash inflow - Discounted Cash outflow > 0
Annual cash inflow * PVAF (8.2%, 11 years) - $440,990 > 0
Annual cash inflow * 7.0702 - $440,990 > 0
Annual cash inflow * 7.0702 > $440,990
Annual cash inflow > $440,990 / 7.0702
Annual cash inflow > $62,373.06
So project should have minimum annual cash flow of $62,373.06 to accept the project