In the context of project management, a task duration is always the same as the amount of work (effort) it takes to finish the task. true or false?

User Alex Vayda
by
8.5k points

1 Answer

1 vote

Answer:

False

Step-by-step explanation:

The statement that says that in the context of project management, a task duration is always the same as the amount of work (effort) it takes to finish the task is false because the effort is the time a person needs to finish a task while the duration is the period of time that a person has to finish it. For example, an employee has a task that takes forty hours of work to finish it but he has a month to do it. In this case, the effort is forty hours but the task duration is one month.