The difference between the upper specification and the lower specification for a process is 0.600.60. The standard deviation is 0.100.10. Based on the givenâ information, the process capabilityâ ratio, Upper C Subscript pCp â= nothing â(round your response to two decimalâ places).

User Trizz
by
4.9k points

1 Answer

2 votes

Answer:

1

Step-by-step explanation:

The computation of the process capability ratio is shown below:

As we know that

Process capability ratio is

= (USL - LSL) ÷ (6 × Standard Deviation)

where USL = Upper Specification Limit

LSL= Lower Specification Limit

Their difference is 0.600

And, the standard deviation is 0.100

Now placing these values to the above formula

So, the process capability ratio is

= 0.600 ÷ (6% × 0.10)

= 1