Answer:
Bidder B is the lower bidder. the option (A) is correct
Step-by-step explanation:
Solution
Given that:
Bidder A = $500,000
The estimate completion time = 200 days
Bidder B = $540,000
The estimate completion time =180 days
Overhead charges = $10,000/day
Now,
The Total Bid of A (including overhead charges) = 500,000 + 200 * 10000
= 500,000 +2000000
=$2,500,000
The Total Bid for B (Including overhead charges) = 540,000 + 180 * 10000
=540,000 +1,800,000
=$2340000
Hence Bidder B is apparently a low bidder, since the Total Bid of B is lower than the Total Bid of A.