A and B can do a piece of work in 30 days, while B and C can do the same work in 24 days and C and A in 20 days. If they all work together, in how many days will the work finish?
asked
Apr 15, 2021
72.2k
views
1
vote
A and B can do a piece of work in 30 days, while B and C can do the same work in 24 days and C and A in 20 days. If they all work together, in how many days will the work finish?
Mathematics
high-school
Ayyappan Sekar
asked
by
Ayyappan Sekar
7.9k
points
answer
comment
share this
share
0 Comments
Please
log in
or
register
to add a comment.
Please
log in
or
register
to answer this question.
1
Answer
5
votes
Answer:
= 120 days
Explanation:
find their LCM
30,24,20
= 120 days
Roasm
answered
Apr 21, 2021
by
Roasm
7.9k
points
ask related question
comment
share this
0 Comments
Please
log in
or
register
to add a comment.
Ask a Question
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.
9.3m
questions
12.0m
answers
Other Questions
How do you can you solve this problem 37 + y = 87; y =
What is .725 as a fraction
A bathtub is being filled with water. After 3 minutes 4/5 of the tub is full. Assuming the rate is constant, how much longer will it take to fill the tub?
Write words to match the expression. 24- ( 6+3)
The cost of 5 similar digital cameras and 3 similar video cameras is 3213. Each video camera costs 4 times as much as each digital camera. John buys a digital camera and a video camera. How much does he
Twitter
WhatsApp
Facebook
Reddit
LinkedIn
Email
Link Copied!
Copy
Search QAmmunity.org