Answer:
Under applied overheads= $302,500
Step-by-step explanation:
Overheads are charged to units produced by the means of an estimated overhead absorption rate. This rate is computed using budgeted overhead and budgeted activity level.
As a result of this, overhead charged to total units product might be over or under absorbed compared to the actual amount incurred.
Overhead absorption rate
=budgeted Overhead/Budgeted labour cost × 100
This already given in the question as 150% of the direct labour rate
= 150% of direct labour cost
Applied overhead= OAR× actual labour cost
= 150% × $565,000=$847,500
Under applied overhead = is the difference between actual overhead and applied overhead
$1,150,000 - $847,500 = $302,500
Under applied overheads= $302,500
Here it is under applied because the applied is less than the actual overhead cost