Answer:
1.8 times the cost of labor.
Explanation:
At the beginning of the year, the rate for overhead was estimated to be ...
(overhead $)/(direct labor $) = $396/$220 = 1.8
The overhead rate is 1.8 times the labor cost.
6.2m questions
8.2m answers