In a reorder point problem where both demand and lead time are variable, demand averages 200 units per day with a daily variance of 64, and lead time averages 6 days with a standard deviation of 1 day. What should the reorder point be for a 95% service level?

User Paccc
by
3.8k points

1 Answer

3 votes

Answer:

~ 1561.235

Step-by-step explanation:

Given :


Z=1.645


d = 200\ \\variance =64

Standard deviation can be determined by the
√(variance )

Standard deviation=SD

=
√(64)\ =\ 8


LT = 6\

σ = 8

Now using the formula


R\ =\ d \ *\ LT\ +Z\ \sqrt{LT^(2)\ +SD^(2) \ +\ d\ \sigma\ ^(2) } \\\\Putting\ the\ respective\ value\ we\ get \\R=200 * 6 + 1.645√(6 * 8^2 + 200 *1^2)

R=1561.235