Countertops Unlimited, a manufacturer of kitchen and bath countertops, had the following information for production last period:

Beginning Work in Process Inventory $25,000
Ending Work in Process Inventory $30,000
Beginning Materials Inventory $16,000
Ending Materials Inventory $14,000
Materials Purchased $205,000
Direct Labor $65,000
Indirect Labor $20,000
Indirect Materials Used $55,000
Factory Rent $35,000
Utilities (Rent and Utilities relate to production facilities) $15,000
Office Supplies $10,000
Administrative Salaries $105,000

Assuming that all manufacturing overhead was applied to Work in Process inventory, Total Manufacturing Costs for the period was: __________

a. $217,000
b. $125,000
c. $342,000
d. $367,000
e. None of the above

User Taniqua
by
7.1k points

1 Answer

3 votes

Answer:

c. $342,000

Step-by-step explanation:

Prepare a Manufacturing Cost Schedule to determine the Total Manufacturing Costs.

Manufacturing Cost Schedule :

Direct Material used ($207,000 - $55,000) $152,000

Direct Labor $65,000

Indirect Labor $20,000

Indirect Materials Used $55,000

Factory Rent $35,000

Utilities (Rent and Utilities relate to production facilities) $15,000

Total Manufacturing Costs $342,000

Raw Materials T - Account (calculation of materials transferred to production)

Debit :

Opening Balance $16,000

Purchases $205,000

Totals $221,000

Credit :

Closing Balance $14,000

Transferred to Work In Process (Balancing figure) $207,000

Totals $221,000

Conclusion :

Total Manufacturing Costs for the period was : $342,000